Arlington gets a lot of deck builders. Some have been pouring footings in this clay for twenty years. Some bought a truck and a nail gun six months ago and put up a website that looks exactly like this one. You can't always tell the difference from a sales visit. You can tell from the questions they ask you and the ones they dodge.

The clay under your yard decides more than you think

Most of Tarrant County sits on expansive clay, the heavy black stuff some people call gumbo. It swells when it's wet and shrinks when it dries out, and in a bad year it can move two or three inches between a wet spring and a dry August. A footing that's poured too shallow, or just dumped into a hole with no real shape to it, moves with that soil. Over a few years you get a deck that rocks, a post that's pulled away from its beam, stairs that don't line up with the landing anymore.

A builder who knows this ground digs past the active zone, usually 24 to 36 inches depending on where you are in the city, and bells the bottom of the footing out wider than the top so the concrete can't be pushed up by swelling clay. Ask how deep they're going and why. If the answer is "however deep the auger goes in an hour," keep looking.

Permits aren't optional, and a builder who tells you otherwise is a red flag

Any deck attached to the house, or built more than about 30 inches above grade, needs a permit through the City of Arlington, and that permit gets inspected at least twice, once at the footings before concrete goes in and again at framing before the boards go down. If you're in Mansfield, Grand Prairie, or one of the other towns nearby, the process is similar but you're dealing with a different building department. If you're in a subdivision with an HOA, which covers a lot of the newer neighborhoods built since the 2000s, there's usually a separate approval for materials and railing style before the city permit even gets pulled.

A contractor who says "we don't bother with permits on small jobs" is telling you two things. First, if something goes wrong, your homeowner's insurance can refuse the claim because the work was unpermitted. Second, nobody with the city ever checked the footings or the ledger attachment. That second part matters more than people think.

The ledger board is where most deck failures start

If the deck attaches to the house, that attachment point, the ledger board, is doing most of the structural work. It needs to be lag-bolted or through-bolted into the house framing, not nailed, spaced roughly every 16 inches, with flashing above it so water runs off the house and not down behind the band joist. Skip the flashing and you get rot in the rim joist that nobody sees until the deck starts to sag on that side, usually three or four years in.

This is the single most common cause of deck collapse nationally, and it's almost always invisible once the decking boards are down. Ask your builder to show you a photo of the ledger attachment and flashing on a past job, or ask to see it in person before the boards go on. A contractor who's done this correctly for years won't mind showing you.

Ask about fasteners, joist spacing, and board thickness before you ask about price

Pressure-treated lumber today is treated with a chemical, usually ACQ, that corrodes plain galvanized or electroplated screws over time. It needs hot-dip galvanized or stainless fasteners, and so do the joist hangers. Cheap fasteners are the kind of corner that saves a contractor fifteen dollars a job and costs you a rusted-out hanger in year six.

  • Joist spacing is typically 16 inches on center for standard decking, but composite boards usually need 12 inches on center or they'll sag and feel springy underfoot within a few years.
  • Decking boards are commonly 5/4-inch pressure-treated lumber or a composite product like Trex or TimberTech, and the two age very differently in Texas heat.
  • Composite boards expand and contract more than wood in our summer swings, which is why the gap between boards and the fastening pattern matter more than people assume.

On staining: new pressure-treated lumber here usually needs 30 to 60 days to dry out enough to take a stain or sealer, depending on how hot and dry the stretch is. A builder who offers to stain it the week it's built either doesn't know that or doesn't care, and either way the finish won't hold.

What to walk away from

A bid that's dramatically lower than two others usually means something's getting skipped, and it's rarely something you'll notice until year three. A contractor who won't put the permit, the footing depth, and the fastener type in writing is giving themselves room to change all three after the deposit clears. No proof of liability insurance is a hard no, full stop, because if a worker gets hurt on your property without it, that liability can land on you. And be wary of anyone who wants the whole job paid upfront in cash before a single post hole gets dug.

Older neighborhoods around Meadowbrook or near downtown Arlington often have decks that were added decades after the house was built, sometimes without a permit at all, and a builder doing repair work there needs to check what's actually in the ground before promising a quick fix. Newer subdivisions out toward Mansfield tend to have more consistent soil prep and sometimes engineered plans already on file, which can make permitting faster. Either way, the questions you ask should be the same.